Moving maintenance off spreadsheets: a practical sequence

Most facilities teams start with a spreadsheet, a shared inbox and a handful of contractor portals. It works while one person holds it all in their head. It stops working when that person is on leave, when two copies of the register disagree, or when an auditor asks when a defect was first reported. This is the sequence I would follow to move it into one system without losing what you already know.

By Arbab Shah, asset and facilities manager. A practitioner's guide, not legal advice. Where it mentions a record keeping rule, it reflects NSW law and guidance as at October 2026. Check what applies in your state and to your buildings.

Signs the spreadsheet has run its course

None of these is a failure of the people involved. They are the limits of a tool that was never built to hold a maintenance history.

The sequence

1. Decide what one record is

Before you move a single row, agree on what an asset is and where it lives. A useful pattern is one record per asset, held at a location you would recognise on a walk: site, building, floor and room. Decide whether a system is one asset or many. A fire hydrant system, for example, can be held as the system with its pumps and valves beneath it. Make these calls once, write them down, and apply them across every site.

2. Clean the register before you move it

Moving a messy register gives you a messy register in a better tool. Work through the sheet and resolve duplicates, assets with no location, and rows that describe a room rather than an asset. For each asset, capture make, model and serial number, and who maintains it, the in house team or a named contractor. Where a detail is not known, mark it as unknown. A blank you can see is better than a guess that looks like a fact.

3. Tie each routine to the rule behind it

This is the step most migrations skip, and it is the one that matters most when someone questions an interval. For each routine, record where its frequency comes from: the manufacturer's recommendations, AS 1851-2012 or an approved performance solution for fire measures in NSW, the public health requirements for warm water systems and cooling towers, or your own risk assessment. A routine that just says "every 6 months" cannot be defended. A routine that names its source can.

4. Bring across history, and label it honestly

Import the history you need to plan the next cycle and to answer the questions you expect: the last service date for each routine, open defects, and recent contractor reports. Keep the original spreadsheets and documents. In the new system, treat imported history as a copy of past records, not as work the system saw happen. That distinction matters later, when a dashboard shows what is up to date. Imported is not the same as verified.

5. Start live work on day one

Do not wait for the history to be perfect. From the day you switch, every new request and every open defect goes into the system, and nowhere else. Live records, created as the work happens, are what build a trustworthy history. A record that shows when a fault was reported, when it was made safe and when it was fixed is worth more than a year of backfilled rows.

6. Bring contractors into the same record

Tell each contractor how jobs will reach them from now on, and where their reports must land. Each report should attach to the job and the asset in your system. Download the reports still sitting in contractor portals and attach them too. Keep your own copy rather than relying on a contractor's portal, because the history has to outlast any contract.

7. Run both for one cycle, then retire the sheet

For one maintenance cycle, check the new system against the old sheet. Every routine that fell due should appear in both. Once they agree, make the spreadsheet read only and archive it with a note saying where the live record now sits. Leaving it editable invites someone to keep using it.

Capture the knowledge that walks out the door

The most valuable thing in a long serving site manager's head is rarely in the spreadsheet. It is the pump that trips if you start it before the valve is open, the roof hatch that needs a key from the tenant, the contractor who must be called before eight. Ask for it while you build the register, and write it as a note on the asset itself, where the next person will find it standing in front of the plant. A history that stays with the asset survives a resignation. One that lives in a person does not.

How long to keep what you move

Different rules set different periods. In NSW, AS 1851 records are kept on site for at least 7 years. A test and tag record is kept at least until the next test. Records for registered plant such as lifts are kept for as long as the plant is used. In aged care, incident records under the Aged Care Rules are kept for 7 years. Across a portfolio, the simplest policy is to keep the full history against each asset for as long as you hold it, and to make sure you can export it if you ever change systems.

A short migration checklist

Start with one site

See how a register comes into FMIQ Nexus, checked row by row before anything is committed. Or book a twenty minute demo and bring one site's spreadsheet.

Common questions

How long does it take to move maintenance off spreadsheets?

It depends far more on the state of your register than on the software. Start with one site. Once its register is clean and its routines are tied to their rules, the remaining sites usually follow the same pattern faster, because the decisions are already made.

Should we import all our old maintenance history?

Import the history you need to plan and defend the next cycle, and keep the originals. Treat imported history as a copy of past records, not as verified work, and label it that way in the new system. Live work from the first day is what builds a trustworthy record.

Can we keep using the spreadsheet alongside the new system?

For one cycle, as a cross check. After that, make the spreadsheet read only and archive it. Two live sources of truth are worse than one imperfect one, because nobody knows which to believe.

What do we do with contractor reports that sit in their portals?

Download them and attach them to the asset or job in your own system. Keep your own copy rather than relying on a contractor's portal, because the history has to outlast the contract.

Does a digital system replace the AS 1851 logbook?

Not yet in NSW. AS 1851 requires a printed and signed record left on site at the end of each routine service, and Building Commission NSW says an electronic register cannot yet replace the physical logbook. The digital record sits alongside it and makes it findable.